Update, Oct. 13, 2026: The Rutherford County Regional Planning Commission voted Monday night, Oct. 12, to approve the data center moratorium resolution and send it on toward the County Commission. Every commissioner called in the roll-call vote voted yes, according to the meeting video posted by RCTV.
Before the vote, commissioners changed the definition of a data center in two ways:
The pause would still last one year. The resolution read at the hearing ends the moratorium on the 365th day after passage unless the County Commission ends it sooner.
The courthouse hearing took about an hour and a half. Before it opened, county planning staff told the commission the purpose was to discuss the moratorium itself, not to write data center regulations. They also gave commissioners three definitions to compare: the county's draft, the one proposed by the Rutherford Neighborhood Alliance, and one from a model ordinance the UT Center for Local Planning released the week before.
More than a dozen residents spoke during the public hearing, including the president of the Rutherford Neighborhood Alliance. Speakers raised water use, power, noise, the county's cedar glades and the chance that the state legislature could limit local control when it convenes in January. Several asked for a longer pause or a permanent ban.
Commissioners then debated how to define a data center. They discussed setting the line by electricity demand instead of floor area, at 5, 10, 20 or 50 megawatts, and whether the county's planned unit development (PUD) process would be enough without a moratorium. The county attorney said he favored keeping the definition broad, without electricity or water thresholds, so it would capture any data center use while keeping the existing exclusions for telecommunications facilities. The commission adopted that approach.
After the vote, a county commissioner reminded the audience that the moratorium covers only unincorporated Rutherford County. Murfreesboro, Smyrna and La Vergne set their own zoning.
County staff told the commission the resolution follows the same path as a zoning amendment. It goes to the County Commission's Public Works Committee, which votes on the planning report rather than the resolution itself, and then to the full County Commission. The full commission must hold another public hearing, advertised at least 15 days ahead, and can still amend the resolution. Earlier in the meeting, staff said rezoning and regulation amendment requests from Oct. 12 are scheduled for the Nov. 12, 2026, Board of Commissioners meeting unless deferred.
The sections below describe the draft as it stood before the Oct. 12 vote.
The draft resolution would apply when a data center campus or building tops 20,000 square feet and uses that space mainly for servers, computing hardware, data storage or digital transmission work.
The definition also tries to keep ordinary business technology from being swept into the pause. It leaves out server rooms and communications gear when that equipment supports another allowed main use of the property. It also leaves out several telecommunications operations, including central offices, network facilities, broadband infrastructure and similar communications-service sites.
If adopted as written, the moratorium would last until the 365th day after passage unless the County Commission ends it earlier or extends it.
County staff say the county is not reacting to a filed project. Draft minutes from the Sept. 28 Planning Commission meeting say county rules do not yet single out data centers, and staff reported no pending applications or inquiries for that use in the unincorporated county.
That is why the story matters. Rutherford County is deciding whether to write rules before a developer brings in a site plan, rather than trying to write them during a fight over a particular property.
The draft resolution points to concerns about energy consumption, noise and land-use compatibility. The Sept. 28 minutes say county staff had consulted with Middle Tennessee Electric, Consolidated Utility District, the county IT director and others, and had toured existing data center facilities while researching the issue.
The 20,000-square-foot line may change before any final county action. The Sept. 28 draft minutes show several commissioners questioning whether building size is the best measure because water use, electricity demand, sound, backup generation and other impacts may matter more than floor area.
Commissioner Laura Clark raised water, electricity and sound as better indicators of community impact, according to the draft minutes. Commissioner Trey Gooch questioned whether a one-year pause could block smaller facilities that do not create the same concerns as a large campus. Staff said the 20,000-square-foot threshold was meant partly to avoid classifying routine business server rooms as data centers.
The same minutes say the proposed pause would give the county time to consult utilities, local municipalities, planning professionals, technical experts and other governments. Staff also told commissioners the moratorium could end before the full year if the county finishes its work sooner.
The Oct. 12 packet also includes a Sept. 27 letter from the Rutherford Neighborhood Alliance, which the draft minutes say was presented during public comment at the Sept. 28 meeting. The group said it supports pausing new data center applications, but asked the county to define covered facilities by electricity and water use rather than floor area, to spell out whether crypto mining and similar uses are included, and to use the pause to build a study plan.
The draft minutes say staff could prepare additional definition language before the next meeting, but no changes to the definition were adopted Sept. 28. Staff also said the original draft contemplated six months, and that a year would give more room for research, coordination and public input.
The Planning Commission has made its recommendation, so the deciding vote now belongs to the County Commission. Residents can speak at the County Commission's advertised public hearing. The resolution can still be amended there, and any data center regulations would be written during the one-year pause.
Related local government and growth coverage from OnlyInMurfreesboro includes Murfreesboro's lot-width and pickleball-court debate, La Vergne's Twinning Station planning case, and Middle Tennessee Electric bill pressure after near-record September heat.
Inside Murfreesboro, Scannell's revised Manchester Pike annexation request removes data centers from its allowed uses, with Planning Commission hearings recommended for Dec. 2.
Not yet. The Regional Planning Commission voted on Oct. 12, 2026 to approve the moratorium resolution, but it does not take effect unless the full County Commission adopts it after its own public hearing.
Any size. On Oct. 12, the Planning Commission removed the draft's 20,000-square-foot threshold. The definition now covers any building or group of buildings whose principal use is operating computer systems, servers and data storage, and it adds crypto mining, blockchain, quantum computing and similar technologies. Telecommunications facilities remain excluded.
No. It covers only unincorporated Rutherford County. Murfreesboro, Smyrna, La Vergne and other cities handle their own zoning.
One year. The resolution ends the pause on the 365th day after passage unless the County Commission ends it sooner.
County draft minutes say staff had received no pending applications or inquiries for data centers in the unincorporated county as of the Sept. 28 Planning Commission meeting.
The resolution goes first to the Public Works Committee and then to the full County Commission, which must hold an advertised public hearing. County staff said rezoning and regulation amendment requests from the Oct. 12 meeting are scheduled for the Nov. 12, 2026, Board of Commissioners meeting unless deferred.
Sources: RCTV video: Rutherford County Regional Planning Commission, Oct. 12, 2026, Rutherford County Planning Commission event page, Rutherford County Planning Commission Oct. 12, 2026 agenda packet, which includes the draft resolution, the Sept. 28, 2026, draft minutes and the Rutherford Neighborhood Alliance letter.
*Illustration: AI-generated image of server racks and a gavel on a zoning map; not a real facility or building.*
709 New Salem Hwy
3956 Blaze Dr
3300 Siegel Rd
100 Bulldog Dr